Where OEE is lost and what could be recovered
OEE by site, the process gaps behind it and the potential value of closing them
Potential value at stake
Potential, not realised savings. Basis: 66 line hours a week x 46 weeks x EUR 250 per line hour
Biggest gap
Site F: 61% OEE
Changeovers wait for tools and sign-off, about 40 minutes longer than at Site A
Strongest practice
Site A: 78% OEE
Changeover kits are prepared before the shift and handed over at a fixed time
Where to start
Changeovers at D, E and F
Three sites hold 53 of the 66 line hours a week at stake
OEE and value at stake by site
Gap to Site A in line hours a week, at 120 planned hours per siteSupporting evidence: process maturity by site
1 Ad hoc · 2 Defined · 3 Followed · 4 Followed and measured, scored on what interviews describe
Why Site F loses time
What operators and shift leads describeWeak process and workaround
No changeover kit is prepared. Operators borrow tools from the next line, which then stops too
What Site A does differently
A kit is ready before the shift, and the shift lead signs off the plan at handover rather than at the line
What to test
Pilot the Site A kit and handover at Site F for six weeks, then compare changeover time and availability